Join Now
Cartoon featuring a pregnant woman wanting LDs for a contract tip onLiquidated Damages Provisions in Contracts

Mastering Liquidated Damages Provisions: Key Elements and Best Practices

Mastering Liquidated Damages Provisions: Key Elements and Best Practices

A liquidated damage provision, aka LDs, provides for a specific fixed damage amount if a specific event occurs. We use these provisions to provide the party with a quick and predictable measure for a specific type of contract breach. They seem simple enough, but LD provisions are anything but simple.

Common Uses of Liquidated Damages Provisions

The most common use of LDs is for delivery delays. If the vendor is late, the vendor has to pay a fixed amount per day or week of delay.

Ensuring Enforceability of Liquidated Damages

Courts are reluctant to enforce LDs. They tend to do so only when narrowly drafted and including all the bells and whistles. To make sure they are enforced, every LD should have these five elements:

  1. A specific breach that triggers the LD.
  2. A precise measurement of the cost unit for the LD.
  3. A precise measurement of time to which the cost applies.
  4. Recitation of the fact that it is not a penalty.
  5. Recitation that the amount of damages would be difficult to determine, the amount is a reasonable estimate, and it is the sole remedy and liability for this breach.

Negotiation Points for Liquidated Damages Provisions

Vendors often ask for a grace period before the LD applies and a cap on the amount. Customers should try to limit the breach period or scope so they have a remedy if it goes on longer. For example, the LD is the sole remedy for a delay of up to 30 days, but any longer is a material default with a different remedy.

Typical Contracts Using Liquidated Damages

I usually see LDs used with equipment and construction-related contracts. I don't see them used very often in other commercial contracts.

Other Resources on Liquidated Damages Provisions

How to Contract

Articles from AmLaw100 Firms

     

 

How to Contract's membership is designed to help you build real-world expertise with commercial contracts. Get access to our comprehensive system of live and on-demand courses, weekly lessons, detailed playbooks, and more. Join today!

Find Out More

Sign up for the How to Contract Newsletter to get discounts, free offers, upcoming training, and lots more! 

 

By entering your email and clicking submit, you agree to our Terms of Service and Privacy Policy.